Enable Sprint #

  • In the Taskboard tab, select the Configuration option. 
  • Go to the Taskboard configuration, and ‘Enable Sprint’ and tap the Update Taskboard button. 

Add Sprint #

  • Go to the taskboard, select the specific task and click the kebab menu.
  • There are two options available such as: Add New Sprint and Sprint Settings.

Create New Sprint #

  • Select Add New Sprint option and you can view the pop-up screen like this. 
  • Here, you must add the Start date and End date along with the no.of. Sprints, then click Create button. 
  • Now, the sprint is created successfully in your task board. 

Sprint Settings #

  • Click Sprint Settings, add Sprint Duration and Sprint Start Day along with Sprint Estimations. 
  • Then, click the Save button.
  • On the right side of the taskboard, you can view the two icons such as Estimation Hours and Original Points.  
  • Click Estimation Hours icon, enter the time period in hours for completing the task and tap Apply button as shown in below.  
  • Set the point-based sprint by clicking Original Points icon on the screen.